July 2026 Update
Construction activities on the streets North of Madden creek including Sacramento, Sans Souci, Oak, and Fern will continue through July. Crews will first install water mains, followed by meter and hydrant installation, and finally paving.
During construction, residents can expect typical construction-related impacts, including temporary traffic control, construction vehicles, equipment activity, and some noise. In addition, there will be heavy dump truck and equipment traffic throughout the neighborhood for the duration of construction.
Work is currently scheduled to occur Monday through Friday between 7:30 a.m. and 6:30 p.m. No work is currently planned during weekends, holidays, or nighttime hours.
At this time, we do not anticipate any disruptions to water service. If future work requires a temporary water shutdown, affected customers will receive advance notification whenever possible.
Due to the narrow and steep roads, the contractor, Vinciguerra Construction, will need to block traffic at their active work zone. All roads will be open overnight and weekends. If necessary, please use alternate routes to access your property during construction.
We appreciate your patience as we complete these important improvements to replace aging water infrastructure, improve system reliability, and strengthen fire protection throughout the Homewood community.
2026 Construction Updates
This summer, TCPUD will begin one of the final phases of our multi-year project to completely rebuild the Madden Creek Water System.
Construction during the next phase will focus on water main upgrades on Cherry, Fern, Oak, Trout, Silver, Sacramento, and Sans Souci. This project will install:
- 7,500+ feet of new larger diameter water mains - shown as blue lines on the map.
- 15 new fire hydrants in locations previously without hydrants - shown in red circles on the map.
- Water meters for all Madden Creek customers. More information about metered billing will be coming soon.
Completed Improvements:
- Phase 1 - Installed an emergency Interconnection between the Madden Creek water system and the adjacent TCPUD McKinney Quail water system to provide a critical backup water supply.
- Phase 2 - Replaced water mains and service lateral lines in the southern portion of the system to improve water distribution and installed fire hydrants and water meters.
- Phase 3 (2025) - Rebuilt over 5,000 feet of the water system and installed 10 new fire hydrants within the Highway 89 right-of-way from Fern Street to South Street, and replaced portions on Sacramento Avenue and Sans Souci Terrace south of Fawn Street.